JCP&L Moving Power Lines Underground in Portions of Somerset County
Grid upgrades will also relocate lines away from hard-to-access railroad tracks
The project involves moving a section of power line extending from JCP&L's
As part of the work:
- The main portion of the power line will be relocated from the railroad tracks to
Route 202 /Mine Brook Road . - Approximately 1,500 feet of the new line will be installed underground due to dense trees and difficult terrain along a portion of the corridor.
- An additional 1,400 feet of new overhead wires and poles will also be installed, and 1,800 feet of existing overhead lines upgraded to stronger, thicker wire that can better handle increased capacity and is more resilient during storms.
New, upgraded lines will also be installed to provide power to an industrial area, supporting regional growth.
Once the work is finished this fall, the new line will decrease the demand on power lines from JCP&L's Greater Crossroads substation. This will provide greater redundancy for those lines, improving service reliability for customers in nearby
JCP&L serves 1.1 million customers in the counties of
FirstEnergy is dedicated to integrity, safety, reliability and operational excellence. Its electric distribution companies form one of the nation's largest investor-owned electric systems, serving customers in
View original content to download multimedia:https://www.prnewswire.com/news-releases/jcpl-moving-power-lines-underground-in-portions-of-somerset-county-302304437.html
SOURCE