Company Announcements

Pan African Resources Plc - Operational Update for the half-year ended December 2025 (H1FY26) & Proposed Initiation of Interim Dividend

        
          Pan African Resources PLC
        

(Incorporated and registered in England
and Wales under the Companies Act 1985
with registered number 3937466 on 25      Pan African Resources Funding CompanyFebruary 2000)                            Limited

Share code on LSE: PAF                    Incorporated in the Republic of South
                                          Africa with limited liability
Share code on JSE: PAN
                                          Registration number: 2012/021237/06
ISIN: GB0004300496
                                          Alpha code: PARI
ADR ticker code: PAFRY

(“Pan African Resources” or the “Company”
or the “Group”)



OPERATIONAL UPDATE FOR THE HALF-YEAR ENDED DECEMBER 2025 (H1FY26) AND PROPOSED INITIATION OF INTERIM DIVIDEND

Pan African is pleased to provide its shareholders and noteholders with an operational update for the half year ended 31 December 2025 (Reporting Period) as well as to announce the initiation of an interim dividend to be approved by the Company’s board of directors (Board) together with the H1FY26 results.

 

KEY FEATURES

    --  Increase in gold production of 51% to 128,296oz (H1FY25: 84,705oz)
    --  Further production increases expected IN H2Fy26, on track to meet full
        year production guidance
    --  Substantially de-geared balance sheet - reduction in net debt of more
        than 65%
    --  INITIATION OF interim dividend PROPOSED - ZA12 cents per share
    --  Definitive Feasibility Study Soweto Cluster project - expected to be
        completed by June 2026

 

SAFETY

    --  Improvement in overall Group safety performance
        o Total Recordable Injury Frequency Rate (TRIFR) improved substantially
          to 4.74 (H1FY25:8.25) per million-man hours
        o Lost Time Injury Frequency Rate (LTIFR) improved to 1.22 (H1FY25:
          1.54) per million-man hours.

 

PRODUCTION

 

    --  Increase in gold production of 51% to 128,296oz (H1FY25: 84,705oz), with
        the Group on track to meet full year production guidance range of
        between 275,000oz and 292,000oz
        o Production at Evander operations improved substantially by 87% to
          21,640oz (H1FY25: 11,551oz), with the subvertical hoisting shaft
          operating at capacity and mining in the high-grade Kinross Channel of
          the Kimberley Reef. Production in H2FY26 is expected to increase
          further with higher mined tonnages
        o Elikhulu achieved excellent results, with production increasing by 14%
          to 29,450oz (H1FY25: 25,725oz)
        o Mogale Tailings Retreatment (MTR) operations at steady state following
          ramp-up in FY25, with production of 21,729oz, approximately 10% lower
          than expected, as a result of mining grades and recoveries impacted by
          the current mining area
          # MTR expansion to 1,000ktpm was successfully commissioned in December
            2025, with increased capacity and improved recoveries expected to
            increase gold production in H2FY26. Going forward annualised
            production from MTR is expected to be between 55-60kozpa
        o Barberton Mines underground production increased by 5% to 32,774oz
          (H1FY25: 31,142oz) and BTRP production remained stable at 7,143oz
          (H1FY25: 7,544oz)
        o Tennant Mines achieved steady state throughput, with production of
          15,560oz (including gold equivalent ounces from the sale of copper
          concentrate). Production in H2FY26 is anticipated to increase to
          approximately 30,000oz as higher-grade ore from open pits replace
          lower grade feed from the Crown Pillar Stockpile (CPS). The average
          expected recovered mining grade in H2FY26 is planned at 2.22g/t
          (H1FY26:1.15g/t).

FINANCIAL

    --  The Group has now substantially de-geared its balance sheet, with
        reduction in net debt of more than 65% to US$49.9m, compared to
        US$150.5m in June 2025
        o Given the prevailing high gold prices, the Group expects to be fully
          de-geared (in terms of net debt) by the end of February 2026. This is
          despite the payment of a record final dividend to shareholders in
          December 2025
    --  All in sustaining cost (AISC) of production for H1FY26 is expected in
        the range of US$1,825/oz -US$1,875/oz at US$/ZAR17.37, (FY26 full year
        guidance: US$1,525/oz to US$1,575/oz at US$/ZAR18.50) negatively
        impacted by:
        o the strengthening of the US$/ZAR exchange rate by 6.1% to US$17.37,
          with an impact of approximately US$115/oz
        o the increase in employee share-based payment expenses, as a result of
          an increase of more than 140% in the Company share price from ZAR11.09
          (GBp45.75) at 30 June 2025 to ZAR26.98 (GBp121.00p) at 2 January 2026
          (approximately US$80/oz)
        o third party material processed at the Evander and MTR operations
          during the period contributing to higher costs, as well as increased
          royalty payments due to the higher gold price received
    --  Increased gold production guided for H2FY26 is anticipated to reduce
        unit costs of production.

PROPOSED INTERIM DIVIDEND FOR THE SIX MONTHS ENDED 31 DECEMBER 2025

    --  Interim cash dividend of ZA12 cents per share (or US0.74488 cents per
        share at an indicative exchange rate of US$/ZAR:16.11 or 0.54745 pence
        per share at an indicative exchange rate of GBP/ZAR:21.92) is intended
        to be approved by the Board together with the interim results for the
        six months ended 31 December 2025. Further information regarding the
        formal declaration of the proposed interim dividend as required in terms
        of the JSE Listings Requirements, including the salient dates, will be
        communicated with the release of the Group’s interim results on 18
        February 2026.

 

FUTURE PRODUCTION GROWTH

    --  A feasibility study to process the Group’s Soweto Cluster Tailings
        Storage Facilities (Soweto TSFs) was successfully completed during the
        Reporting Period (announced on SENS and RNS on 27 November 2025). An
        integrated 600ktpm Soweto Tailings Retreatment (STR) circuit at MTR was
        identified as the preferred option to process the Soweto TSFs, due to a
        significantly lower upfront capital requirement, a shorter construction
        period, reduced permitting obligations and superior financial returns.
        This option will also benefit from synergies with the existing MTR plant
        and operational infrastructure
        o The Definitive Feasibility Study for this option is expected to be
          completed by June 2026, with a final Board decision to commence
          project construction shortly thereafter
        o Anticipated construction period of approximately 24 months
        o Expected annual gold production of 30-35koz for approximately 15 years
          at an all-in-sustaining-cost (AISC) of between US$1,000/oz and
          US$1,200/oz, which will increase production from the MTR complex to
          approximately 100kozpa, once construction is complete

    --  At Tennant Mines, the earn-in exploration joint venture with ASX listed
        Emmerson Resources on which the White Devil project and others are
        located was successfully concluded during September 2025
        o Ongoing exploration on the Group’s wholly owned Mining Leases at
          Nobles, Juno and Warrego confirmed extensions to the known mineralised
          zones. Additionally, regional exploration programmes comprising
          magnetotelluric geophysical surveys and remote sensing has identified
          more than 10 new prospective targets for exploration.

ENVIRONMENTAL, SOCIAL AND GOVERNANCE UPDATES

    --  Following the completion of positive feasibility studies for the 20MW
        Evander Mines’ phase 2 solar plant expansion, total solar generation
        capacity at Evander will be expanded from 10MW to 30MW. A contractor has
        been appointed and construction of the additional capacity is expected
        to commence by June 2026
    --  In July 2025, site work commenced on phase 2 of the 3ML/day Evander
        water treatment plant, with first water expected in late February 2026.
        At MTR, construction of a 3ML/day water treatment plant to treat acid
        mine drainage water commenced in November 2025. This plant is expected
        to be commissioned in May 2026 and will produce potable water to meet
        the requirements of the MTR processing plant
    --  The MTR operation was awarded the ‘Best ESG Initiative by a Mining
        Company’ at the international Resourcing Tomorrow conference held in
        December 2025, where competing entries included projects from other
        international mining groups. The judges recognised the immediate
        positive impacts of Pan African's activities on the environment and
        local communities, following years of neglect in the area.

Pan African Resources CEO Cobus Loots commented:

“Pan African’s safety, operational and financial performance in the first half of the financial year, together with the boon of record gold prices, has positioned us to deliver outstanding results for the full year. During the reporting period the Group de-geared its balance sheet and is also now further boosting cash returns to shareholders, with our board set to approve an attractive proposed interim dividend payment.

The half year results demonstrate the success of our strategy of focusing on high-margin, long-life tailings retreatment operations and also the acquisition of the very prospective Tennant Mining in Australia.   We also wish to commend the Evander management team for the successful turnaround of the underground operation, with further improvements expected in the period ahead.

Despite our continued focus on cost control, all-in sustaining unit costs were higher than guided for the reasons detailed in this release, we believe the expected increased gold production in H2 of the financial year will assist with reducing unit costs.

We are excited about the further production growth opportunities within our asset portfolio. Pan African is capitalising on the very favourable current environment to position the Group to continue “Mining for a Future” for many more years.

We look forward to presenting our interim results, including details on our prospects and initiatives, on 18 February 2026.”

The information contained in this announcement is the responsibility of the Company’s Board and has not been reviewed or reported on by the Group’s external auditors.

 

Johannesburg

 

26 January 2026

 

For further information on Pan African, please visit the Company's website at

www.panafricanresources.com

 ___________________________________________________________________________
|Corporate information                                                      |
|___________________________________________________________________________|
|Corporate Office                      |                                    |
|                                      |                                    |
|The Firs Building                     |Registered Office                   |
|                                      |                                    |
|2nd Floor, Office 204                 |107 Cheapside, 2nd Floor            |
|                                      |                                    |
|Corner Cradock and Biermann Avenues   |London, EC2V 6DN                    |
|                                      |                                    |
|Rosebank, Johannesburg                |United Kingdom                      |
|                                      |                                    |
|South Africa                          |Office: + 44 (0)20 3869 0706        |
|                                      |                                    |
|Office: + 27 (0)11 243 2900           |jane.kirton@corpserv.co.uk          |
|                                      |                                    |
|info@paf.co.za                        |                                    |
|______________________________________|____________________________________|
|Chief Executive Officer               |Financial Director and debt officer |
|                                      |                                    |
|Cobus Loots                           |Marileen Kok                        |
|                                      |                                    |
|Office: + 27 (0)11 243 2900           |Office: + 27 (0)11 243 2900         |
|______________________________________|____________________________________|
|Head: Investor Relations              |                                    |
|                                      |                                    |
|Hethen Hira                           |Website: www.panafricanresources.com|
|Tel: + 27 (0)11 243 2900              |                                    |
|E-mail: hhira@paf.co.za               |                                    |
|______________________________________|____________________________________|
|Company Secretary                     |Joint Broker                        |
|                                      |                                    |
|Jane Kirton                           |Ross Allister/Georgia Langoulant    |
|                                      |                                    |
|St James's Corporate Services Limited |Peel Hunt LLP                       |
|                                      |                                    |
|Office: + 44 (0)20 3869 0706          |Office: +44 (0)20 7418 8900         |
|______________________________________|____________________________________|
|JSE Sponsor & JSE Debt Sponsor        |Joint Broker                        |
|                                      |                                    |
|Ciska Kloppers                        |Thomas Rider/Nick Macann            |
|                                      |                                    |
|Questco Corporate Advisory Proprietary|BMO Capital Markets Limited         |
|Limited                               |                                    |
|                                      |Office: +44 (0)20 7236 1010         |
|Office: + 27 (0) 63 482 3802          |                                    |
|______________________________________|____________________________________|
|                                      |Joint Broker                        |
|                                      |                                    |
|                                      |Matthew Armitt/Jennifer Lee         |
|                                      |                                    |
|                                      |Joh. Berenberg, Gossler & Co KG     |
|                                      |(Berenberg)                         |
|                                      |                                    |
|                                      |Office: +44 (0)20 3207 7800         |
|______________________________________|____________________________________|