Following Successful 2025, E3 Lithium Provides Operational Update and 2026 Outlook
Advancing Technical, Commercial, and Regulatory Initiatives are Key Goals for E3’s
“E3 hit major milestones in 2025, culminating in the construction and operation of our Demonstration Facility leading to production of battery-grade lithium carbonate and kicking off our commercial permitting,” said
2025 HIGHLIGHTS
- Constructed and commissioned Phase 1 of the Demonstration Facility
- Produced battery-grade lithium carbonate from the Demonstration Facility
- Executed commercial agreement for potential sale of lithium carbonate and supply of sorbents
- Submitted EPEA application for the Clearwater Project Facility
-
Raised a combined
~$20 million to support advancement of the project - Continued to strengthen leadership team to support execution of the project
2026 KEY OBJECTIVES
- Deliver battery-grade lithium carbonate to global customers to support offtake agreement execution
- Complete the Demonstration Facility which informs engineering and the delivery of Front-End Engineering Design and the Feasibility Study
- Advance Front-End Engineering Design and complete the Clearwater Feasibility Study
- Continue the permitting and stakeholder engagement process, with Directive 056 Clearwater facility licence submitted in early 2026
Throughout 2025, the Company made significant progress to advance technical, commercial, and regulatory plans for its
Demonstration Facility Commissioned
E3’s technical successes included converting a concept into reality by completing the design of its facility based on the Pre-Feasibility Study (“PFS”) conducted in 2024. The Company completed and commissioned Phase 1 of its Demonstration Facility and produced battery-grade lithium carbonate in the third quarter of 2025.
Battery-Grade Lithium Carbonate Production and
The Company continued to make progress on its commercial plans, consistently producing battery-grade lithium carbonate and delivering samples to key strategic global off-takers earlier this year. This is a critical step as the Company builds relationships with key players in the battery and critical minerals industry within the global lithium market. Securing certain offtake agreements will materially advance the commercialization of E3 Lithium’s
Major Permits Submission
In late 2025, the Company submitted its Environmental Protection and Enhancement Act (“EPEA”) application and most recently submitted its application for the Directive 056 (“D56”) facility licence through the
Management Evolution
During 2025,
2026 Outlook
E3's overarching goal for 2026 is to advance the
The key 2026 milestones for
Strategic Engagement
In parallel with both technical and regulatory advancements, the Company will continue to progress discussions with key offtake partners to execute offtake agreements and advance project financing initiatives. This will include continued delivery of battery-grade lithium carbonate being produced from the Company’s Demonstration Facility and continued engagement with strategic capital providers as it evaluates project financing.
Demonstration Facility
E3 is currently executing Phase 2 of its Demonstration Facility. The final completion activities for the two wells drilled in the later part of 2025 are underway. A tie-in between the two wells and the equipment required to complete gas and water analysis will be installed shortly thereafter and a reservoir production test will then commence. Brine produced through the reservoir test will be available to continue operating the Direct Lithium Extraction (“DLE”) and polishing & carbonation equipment, which was commissioned in the fall of 2025. Data from the Demonstration Facility will be used for the completion of FEED and the subsequent FS report. Battery-grade lithium carbonate will also be continually shipped to key potential strategic partners and off-takers as part of the pre-qualification process.
Complete Front-End Engineering Design and Feasibility Study
The Company continues to advance its technical designs for the commercial facility, with the focus for the balance of 2026 on the completion of FEED and publishing its FS shortly thereafter. This work enables E3 to complete a Class 3 cost estimate, necessary for financial institutions and strategic partners interested in supporting the project financing for the construction of the Clearwater facility. The Company has selected the lead firm to complete this engineering work for the
Permitting
The Company will continue the permitting process and engagement with its stakeholders around the Clearwater facility and project site. E3 aims to have submitted all remaining licence applications required for the construction and operation of the
Finally, the Company recently entered into an agreement with
ON BEHALF OF THE BOARD OF DIRECTORS
About
1:
The Clearwater Project NI 43-101 Pre-Feasibility Study, effective
2:
The mineral resource NI 43-101 Technical Report for the Garrington District Lithium Resource Estimate, effective
Unless otherwise indicated,
Forward-Looking and Cautionary Statements
This news release includes certain forward-looking statements as well as management’s objectives, strategies, beliefs and intentions or forward-looking information within the meaning of applicable securities laws. Forward-looking statements are frequently identified by such words as “believe”, “may”, “will”, “plan”, “expect”, “anticipate”, “estimate”, “intend”, “project”, “potential”, “possible” and similar words referring to future events and results. Forward-looking statements are based on the current opinions, expectations, estimates and assumptions of management in light of its experience, perception of historical trends, and results of the PFS, but such statements are not guarantees of future performance. In particular, this news release contains forward-looking information relating to: the expected timelines for execution of offtake agreements, completion of Phase 2 of the Demonstration Facility, completion of FEED and FS, submitting all remaining licence applications, and commissioning and commercial operations of E3’s
All forward-looking information (including future-orientated financial information) is inherently uncertain and subject to a variety of assumptions, risks and uncertainties, including the speculative nature of mineral exploration and development, fluctuating commodity prices, the effectiveness and feasibility of emerging lithium extraction technologies which have not yet been tested or proven on a commercial scale or on the Company’s brine, risks related to the availability of financing on commercially reasonable terms and the expected use of proceeds; operations and contractual obligations; changes in estimated mineral reserves or mineral resources; future prices of lithium and other metals; availability of third party contractors; availability of equipment; failure of equipment to operate as anticipated; accidents, effects of weather and other natural phenomena and other risks associated with the mineral exploration industry; the Company’s lack of operating revenues; currency fluctuations; risks related to dependence on key personnel; estimates used in financial statements proving to be incorrect; competitive risks and the availability of financing, as described in more detail in our recent securities filings available under the Company’s profile on SEDAR+ (www.sedarplus.ca). Actual events or results may differ materially from those projected in the forward-looking statements and we caution against placing undue reliance thereon. We assume no obligation to revise or update these forward-looking statements except as required by applicable law.
View source version on businesswire.com: https://www.businesswire.com/news/home/20260129712325/en/